Piggs Peak Delivery Roads
October 30, 2023
Works for World vision
October 30, 2023





| ASSIGNMENT NAME: Construction Supervision of the Rehabilitation of Titandini Road Phase II in Mankayane | COUNTRY: Swaziland | ||||||
| LOCATION WITHIN COUNTRY: Mankayane, Manzini Region | PROFESSIONAL STAFF PROVIDED BY THE FIRM: Project Manager, Resident Engineer | ||||||
| NAME OF CLIENT: Mankayane Town Board | NO. OF STAFF : 2 | ||||||
| ADDRESS: P. O. Box 388MANKAYANEM206 | NO. OF STAFF-MONTHS: 5 | DURATION OF ASSIGNMENT: 5 | |||||
| START DATE: May 2018 | COMPLETION DATE: September 2018 | APPROXIMATE VALUE OF SERVICES (US Dollars): Professional fees 13 201.67Construction costs $190 906.64 | |||||
| NAME OF ASSOCIATED CONSULTANTS: I. C. Development – Environmentalist | PROFESSIONAL STAFF-MONTHS OF ASSOCIATED CONSULTANTS: 1 | ||||||
| NAME OF SENIOR STAFF (PROJECT DIRECTOR/COORDINATOR, TEAM LEADER) INVOLVED AND FUNCTIONS PERFORMED: | |||||||
| Project Director Resident Engineer Environmentalist | : : : | S. Makhubu A. Vilakati C. van Zuydam | – – – | Client liaison, contract management and administration and professional responsibility Responsible for overall construction supervision Responsible for environmental compliance | |||
| NARRATIVE DESCRIPTION OF PROJECT: The project is the upgrading of a 220m gravel road to a surfaced road as well as the reconstruction of a 60m surfaced road section. Roadworks comprised of the removal of the existing asphalt surfacing (where necessary), cut to spoil of approximately 100m³ of existing material and replacing it with a 150mm in-situ selected layer, 150mm cement stabilized sub-base layer, 150mm crushed stone and a 30mm continuously graded asphalt layer, together with kerbs on one side and concrete open drain on the other. | |||||||
| DESCRIPTION OF ACTUAL SERVICES PROVIDED BY THE FIRM: Services provided included project management and construction supervision. | |||||||